← All projects

Pawana Falyan PSP

Study terms approved (ToR) (as of 13 September 2024) · Avaada Aqua Batteries Pvt Ltd (Avaada Group)

2,400MW

Not disclosedtrees to be felled

129ha of forest land

2villages named

  1. MoU signed
  2. Study terms (ToR)
  3. Forest clearance
  4. Construction
  5. Operating
Forest (ha) 129 Documented“Stage I FC for 129 Ha of forest land involved in the project shall be submitted.”EAC 15th meeting minutes, 13 Sep 2024 (Pawana Falyan ToR, item 15.1), page10 · 13 September 2024
Total land (ha) 204 Documented“Loop Pumped Storage Project (1500 MW) in an area of 204Ha in Village Kurvande and Falyan, Sub”EAC 15th meeting minutes, 13 Sep 2024 (Pawana Falyan ToR, item 15.1), page2 · 13 September 2024
Capacity (MW) 2,400 Reported“…two major pumped storage hydro projects (PSHPs) with a total capacity of 3,650 MW. The agreement includes the development of the 2,400 MW Pawana Falyan pumped storage project (PSP) and the 1,200 MW Sirsala PSP. The cumulative investment for these projects is rep…”Renewable Watch: Avaada MoU for 3.65 GW · 30 April 2025
Location18.7036°N, 73.3942°E (approx)Documented“geographical latitude 18°42'13.1" N and longitude 73°23'39.2"E. Whereas, the proposed lower”Approximate location; the source gives a point near the project, not its dam coordinates.EAC 15th meeting minutes, 13 Sep 2024 (Pawana Falyan ToR, item 15.1), page2 · 13 September 2024
DistrictPune, Raigad, Mawal, Sudhagad
VillagesKurvande, Falyan
MoU signed29 April 2025

Sources disagree

Capacity (MW)

Capacity raised between the Aug 2024 and Apr 2025 MoUs; the ToR (Sep 2024, per Annexure 1) is for 1,500 MW.

Notes

  • First Memorandum of understanding (MoU) A non-binding agreement between the state and a developer to study and build a project at a site, with a water allocation. More in glossary → Aug 2024 at 1,500 MW, raised to 2,400 MW in the Apr 2025 MoU (with the 1,200 MW Sirsala project).
  • Annexure 1 lists Pawana Falyan (Avaada Hydropower Battery Pvt Ltd, Pune and Raigad) at 1,500 MW with Terms of Reference (ToR) The list of studies an EIA must cover, set by the expert committee. Getting a ToR is the first clearance step, not a permission to build. More in glossary → granted, which supports the earlier Power Peak Digest report of ToR on 13 Sep 2024.
  • The ToR is for the 1,500 MW layout.
  • Expert Appraisal Committee (EAC) The central committee of experts that recommends ToR and EC for river valley and hydro projects, including PSPs. More in glossary → 15th minutes (item 15.1, proposal IA/MH/RIV/470300/2024): ToR for 1,500 MW Closed loop A PSP whose two reservoirs are built away from rivers; water is filled once and then recirculated. More in glossary → on 204 ha, about 63% (129 ha) forest.
  • The minutes give the upper reservoir longitude two ways (73°23'39.2" and 73°23'29.2"), so coords are approx.

Timeline

Category
  1. · MoU signed, no clearance yet Reported #

    Avaada signs MoU for Pawana Falyan (2,400 MW) and Sirsala (1,200 MW)

    Details and documents

    Pawana Falyan was 1,500 MWReported“…urces Department of Maharashtra and Avaada Aqua Batteries Private Limited, a subsidiary of Avaada Group. The projects include the 1,500 MW Pawana Falyan PSP located in Pune and Raigad districts, and the 1,250 MW Kumbhavade PSP in Kolhapur and Ratnagiri districts. T…”Powerline: Avaada's Aug 2024 MoU (Pawana Falyan 1,500 MW) in Avaada's Aug 2024 MoU.Reported“…two major pumped storage hydro projects (PSHPs) with a total capacity of 3,650 MW. The agreement includes the development of the 2,400 MW Pawana Falyan pumped storage project (PSP) and the 1,200 MW Sirsala PSP. The cumulative investment for these projects is rep…”Renewable Watch: Avaada MoU for 3.65 GW · 30 April 2025Reported“…l capacity of 3,650 MW. The agreement includes the development of the 2,400 MW Pawana Falyan pumped storage project (PSP) and the 1,200 MW Sirsala PSP. The cumulative investment for these projects is reportedly estimated at Rs 151 billion. The initiative is expec…”Renewable Watch: Avaada MoU for 3.65 GW · 30 April 2025

    Pawana Falyan PSP · Powerline: Avaada's Aug 2024 MoU (Pawana Falyan 1,500 MW) · Renewable Watch: Avaada MoU for 3.65 GW

  2. · Clearance Reported #

    EAC recommends ToR for Pawana Falyan Pumped storage project (PSP) Two reservoirs at different heights: water is pumped up when power is cheap and released through turbines when power is needed. More in glossary →

    Details and documents

    The EAC's 15th meeting recommended ToR for Avaada's 1,500 MWReported“one for the proposed 1500MW Pawana Falyan Pumped Storage Hydro Project and selected for”EAC 15th meeting minutes, 13 Sep 2024 (item 15.1), page6 · 13 September 2024 Pawana Falyan PSP on 204 haReported“Loop Pumped Storage Project (1500 MW) in an area of 204Ha in Village Kurvande and Falyan, Sub”EAC 15th meeting minutes, 13 Sep 2024 (item 15.1), page2 · 13 September 2024, of which 129 haReported“Stage I FC for 129 Ha of forest land involved in the project shall be submitted.”EAC 15th meeting minutes, 13 Sep 2024 (item 15.1), page10 · 13 September 2024 is forest.

    Pawana Falyan PSP · EAC 15th meeting minutes, 13 Sep 2024 (item 15.1) · Annexure 1, 'Pumped storage projects in Maharashtra' (Marathi; source document not yet traced, via social media screenshot)

  3. · MoU signed, no clearance yet Reported #

    Avaada signs MoU for Pawana Falyan (1,500 MW) and Kumbhavade (1,250 MW)

    Details and documents

    Non-binding MoU with WRD for 2,750 MWReported“Avaada Group has signed a non-binding memorandum of understanding (MoU) with the Maharashtra government to develop two pumped storage projects (PSPs) with a combined capacity of 2,750 MW.”Power Line: Avaada MoU for two PSPs (2,750 MW) · 14 August 2024. Pawana Falyan, in the Pune–Raigad Ghats, was raised to 2,400 MWReported“…two major pumped storage hydro projects (PSHPs) with a total capacity of 3,650 MW. The agreement includes the development of the 2,400 MW Pawana Falyan pumped storage project (PSP) and the 1,200 MW Sirsala PSP. The cumulative investment for these projects is rep…”Renewable Watch: Avaada's Apr 2025 MoU (Pawana Falyan 2,400 MW) in 2025.Reported“…urces Department of Maharashtra and Avaada Aqua Batteries Private Limited, a subsidiary of Avaada Group. The projects include the 1,500 MW Pawana Falyan PSP located in Pune and Raigad districts, and the 1,250 MW Kumbhavade PSP in Kolhapur and Ratnagiri districts. T…”Power Line: Avaada MoU for two PSPs (2,750 MW) · 14 August 2024Reported“…, a subsidiary of Avaada Group. The projects include the 1,500 MW Pawana Falyan PSP located in Pune and Raigad districts, and the 1,250 MW Kumbhavade PSP in Kolhapur and Ratnagiri districts. The total investment for these projects is estimated at approximately Rs 1…”Power Line: Avaada MoU for two PSPs (2,750 MW) · 14 August 2024

    Pawana Falyan PSP · Renewable Watch: Avaada's Apr 2025 MoU (Pawana Falyan 2,400 MW) · Power Line: Avaada MoU for two PSPs (2,750 MW)

Sources

Confidence: verified