Koyna–Nivakane PSP
2,700MW
Not disclosedtrees to be felled
0ha of forest land
2villages named
- MoU signed
- Study terms (ToR)
- Environment clearance
- Forest clearance
- Construction
- Operating
| Forest (ha) | 0 Documented“Forest Land 0.00 ha”EAC 58th meeting minutes, 15 Jul 2026 (Nivakane EC, item 58.1), page238 · 15 July 2026 |
|---|---|
| Total land (ha) | 361.82 Documented“Pumped Storage Project (2700 MW) in an area of 361.82ha at Village Marathwadi, Tehsil Patan,”EAC 58th meeting minutes, 15 Jul 2026 (Nivakane EC, item 58.1), page75 · 15 July 2026 |
| Capacity (MW) | 2,700 Reported“…of Environment, Forest and Climate Change (MoEFCC) has recommended Environmental Clearance (EC) for Adani Green Energy Limited's 2,700 MW Nivakane (Integrated) Pumped Storage Project in Satara district, Maharashtra. The Rs 14,952 crore project, proposed near Mar…”Power Peak Digest: EAC clears Adani's Nivakane PSP near tiger reserve buffer · 5 August 2026 |
| Cost (₹ crore) | 14,952 Reported“…for Adani Green Energy Limited's 2,700 MW Nivakane (Integrated) Pumped Storage Project in Satara district, Maharashtra. The Rs 14,952 crore project, proposed near Marathwadi and Nivakane villages in Patan tehsil, will be developed as an off-stream closed-loop pum…”Power Peak Digest: EAC clears Adani's Nivakane PSP near tiger reserve buffer · 5 August 2026 |
| Location | 17.4831°N, 73.8436°E (exact)Documented“Geographical Co-Ordinates Proposed Upper Reservoir 17°28'59.18"N”EAC 58th meeting minutes, 15 Jul 2026 (Nivakane EC, item 58.1), page51 · 15 July 2026 |
| District | Satara, Patan |
| Villages | Nivakane, Marathwadi |
| Nearest protected area | Sahyadri Tiger Reserve (buffer zone), 0.15 km Reported |
Notes
- Now the 'Nivakane (Integrated) Pumped storage project (PSP) Two reservoirs at different heights: water is pumped up when power is cheap and released through turbines when power is needed. More in glossary → '.
- Terms of Reference (ToR) The list of studies an EIA must cover, set by the expert committee. Getting a ToR is the first clearance step, not a permission to build. More in glossary → amended 11 Jul 2025 from 2,450 MW on 312.84 ha to 2,700 MW on 361.82 ha after the lower dam moved.
- Expert Appraisal Committee (EAC) The central committee of experts that recommends ToR and EC for river valley and hydro projects, including PSPs. More in glossary → sub-committee EAC site visit An inspection by EAC members. Since Sep 2024 the EAC wants one for every Western Ghats PSP before EC. More in glossary → 26 Nov 2024.
- EAC recommended Environmental clearance (EC) The environment ministry's permission for a project, given after the EIA and public hearing, with conditions attached. More in glossary → on 15 Jul 2026 on condition of prior National Board for Wildlife (NBWL) The body chaired by the Prime Minister whose Standing Committee must approve projects in or near protected areas. More in glossary → Standing Committee clearance; the site is ~150 m from the Western Ghats / Sahyadri The 1,600 km mountain chain along India's west coast: older than the Himalaya, a UNESCO World Heritage site and a global biodiversity hotspot. More in glossary → Wildlife sanctuary (WLS) and tiger reserve Protected areas under the Wild Life (Protection) Act. A tiger reserve has an inviolate core and a surrounding buffer. More in glossary → buffer.
- Land reported as non-forest private land (forest 0 ha per Power Peak Digest; EAC minutes not yet read).
- EAC 58th minutes (item 58.1, proposal IA/MH/RIV/580995/2026) confirm 361.82 ha, all non-forest, and ~0.15 km from the Sahyadri Tiger Reserve buffer.
Timeline
-
EAC recommends EC for Adani's Nivakane PSP, 150 m from tiger reserve buffer
Details and documents
The 2,700 MWReported“…of Environment, Forest and Climate Change (MoEFCC) has recommended Environmental Clearance (EC) for Adani Green Energy Limited's 2,700 MW Nivakane (Integrated) Pumped Storage Project in Satara district, Maharashtra. The Rs 14,952 crore project, proposed near Mar…”Power Peak Digest · 5 August 2026 Nivakane (Integrated) PSP in Patan, Satara, on 361.82 haReported“…r conductor system will include five steel-lined pressure shafts bifurcating into 10 unit pressure tunnels. The scheme requires 361.82 hectares of non-forest private land. Water for initial filling will be sourced from the Sakhari-Chiteghar Dam, comprising 29.57 M…”Power Peak Digest · 5 August 2026 reported as non-forest private land, was recommended for EC on condition that the NBWL Standing Committee clears it before construction. The site is about 150 mReported“…:46 pm IST Facebook Twitter WhatsApp Linkedin Follow Us : Text Size: A- A+ --> New Delhi, Jul 29 (PTI) Located about 150 metres from the Sahyadri Tiger Reserve's buffer zone, a pumped storage project (PSP) by Adani Green Energy Limited (AGEL) in Maha…”ThePrint (PTI) · 29 July 2026 from the Sahyadri Tiger Reserve buffer.