Shirawta PSP

Environmental clearance granted (as of 15 June 2026) · Tata Power

1,800MW

64,729trees to be felled

160.78ha of forest land

3villages named

  1. MoU signed
  2. Study terms (ToR)
  3. Environment clearance
  4. Construction
  5. Operating
Trees 64,729 Documented“0.7 (Very Dense Forest) of Eco Class I and 64729 number of trees are”FAC (Advisory Committee) minutes, 8 May 2026, MoM ID FC/MOM/AC/969417/2026: '64729 number of trees are proposed to be felled', page92 · 8 May 2026 Documented
Forest (ha) 160.78 Documented“for diversion of 160.783 ha. forest land for construction of Shirawta Off Stream”FAC (Advisory Committee) minutes, 8 May 2026, MoM ID FC/MOM/AC/969417/2026 (Shirawta Stage-I recommended), page92 · 8 May 2026
Total land (ha) 197.8 Documented“197.797 ha at Village Khandshi, Rakaswadi, Thoran etc, Sub-district Mawal, District Pune,”Shirawta EC letter, 15 Jun 2026 (MoEFCC), page1 · 15 June 2026
Capacity (MW) 1,800 Documented“c) CEA/CWC accorded concurrence to Shirawta PSP (1800 MW) vide Office”Shirawta EC letter, 15 Jun 2026 (MoEFCC), page15 · 15 June 2026
Storage (GWh) 10.8 Documented“b c Storage capacity 10800 MWH”Shirawta draft EIA executive summary (MPCB), Sep 2024, page4 · September 2024
Cost (₹ crore) 7,285 Documented“x. Project Cost: The estimated project cost is Rs 7285.0 crore. Total capital cost earmarked”EAC minutes, Sep 2025 (Shirawta), page3 · 26 September 2025
Location18.8406°N, 73.4544°E (exact)Documented“v. Project location: The geographical co-ordinate of the project are Latitude: 18°50' 26.26" N”Shirawta EC letter, 15 Jun 2026 (MoEFCC), page13 · 15 June 2026
DistrictPune, Maval
VillagesKhandshi, Rakaswadi, Thoran
Nearest protected areaBhimashankar Wildlife Sanctuary, 19.7 km Official claim
MoU signedAugust 2023

Sources disagree

Cost (₹ crore)

A ₹11,000 crore figure used earlier had no source and was dropped.

Notes

  • 81% of the site is forest: 160.783 ha (157.157 ha reserve forest, 3.626 ha private forest) of 197.797 ha; the 37.014 ha non-forest land is Tata Power's own.
  • Lower reservoir is the existing Shirawta dam.
  • Expert Appraisal Committee (EAC) The central committee of experts that recommends ToR and EC for river valley and hydro projects, including PSPs. More in glossary → EAC site visit An inspection by EAC members. Since Sep 2024 the EAC wants one for every Western Ghats PSP before EC. More in glossary → 23 Feb 2024 (per SANDRP); Public hearing A meeting near the project site, run by the state pollution control board, where affected people can object on record. More in glossary → 29 Oct 2024 at Khandshi; EAC recommended Environmental clearance (EC) The environment ministry's permission for a project, given after the EIA and public hearing, with conditions attached. More in glossary → 26 Sep 2025; EC granted 15 Jun 2026.
  • Forest proposal FP/MH/HYD/IRRIG/477051/2024: the forest is ' Canopy density / very dense forest How much of the ground the tree crowns cover. 70% or more is 'very dense forest' in India's forest survey. More in glossary → ' (canopy 0.7, Eco Class I) and 64,729 trees are to be felled; 130.669 ha of it is the upper reservoir.
  • The Forest Advisory Committee (FAC) The central committee that recommends whether forest land may be diverted for a project. More in glossary → deferred Forest clearance (Stage-I / Stage-II) Central permission to use forest land for a project. Stage-I is in-principle approval with conditions; Stage-II is final approval. More in glossary → on 24 Mar 2026 (asked for the Western Ghats Ecologically Sensitive Area (ESA) About 56,825 sq km of the Western Ghats proposed for protection since 2014; still only a draft, reissued six times. More in glossary → division's view) and recommended it on 8 May 2026, after the Eco-sensitive zone (ESZ) A notified buffer around a sanctuary or national park where some activities are banned or regulated. More in glossary → division said Pumped storage project (PSP) Two reservoirs at different heights: water is pumped up when power is cheap and released through turbines when power is needed. More in glossary → are a 'regulated activity' in the draft ESA.
  • So Stage-I was recommended before the 15 Jun EC; the date of the Stage-I letter itself is not known.
  • Compensatory afforestation (CA) and CAMPA Planting on other land to 'replace' forest that is cut. The developer pays; the money goes to a state CAMPA fund. More in glossary → is 160.783 ha of Tata Power's own land at Tata Talav, Mulshi, which already has tree cover (density 0.4), so only a protection plan (₹7.33 cr) is proposed.
  • The FAC noted Karjat (Saidongar-1) is 5.82 km away; the state said the two are in different basins.
  • Works reported to start July 2026.

Timeline

Category
  1. · Clearance Documented #

    Environmental clearance granted to Tata's Shirawta PSP

    Details and documents

    MoEFCC granted EC for the 1,800 MWDocumented“c) CEA/CWC accorded concurrence to Shirawta PSP (1800 MW) vide Office”Shirawta EC letter, 15 Jun 2026, page15 · 15 June 2026 project on 197.797 haDocumented“197.797 ha at Village Khandshi, Rakaswadi, Thoran etc, Sub-district Mawal, District Pune,”Shirawta EC letter, 15 Jun 2026, page1 · 15 June 2026, 160.783 haDocumented“various project components, out of which 160.783 ha is forest land and 37.014 ha is non-”Shirawta EC letter, 15 Jun 2026, page14 · 15 June 2026 of it forest. The EC requires Stage-I forest clearance 'before grant of EC', but its annexure lists the forest proposal as pending and Forest Rights Act (FRA) The 2006 law that recognises tribal and forest-dwelling communities' rights over the land and forests they use. More in glossary → as under progress; whether Stage-I came first is not stated.

    Shirawta PSP · Shirawta EC letter, 15 Jun 2026

  2. · Clearance Reported #

    EAC team visits Bhivpuri and Shirawta sites

    Details and documents

    The EAC visited the Tata Power Bhivpuri and Shirawta sites on 23 Feb 2024 while appraising their ToRs, seven months before its Western Ghats / Sahyadri The 1,600 km mountain chain along India's west coast: older than the Himalaya, a UNESCO World Heritage site and a global biodiversity hotspot. More in glossary → site-visit rule. No later visit is listed for either project before their ECs.

    Bhivpuri PSP · Shirawta PSP · SANDRP: EAC & FAC decisions in 2024 (20 Mar 2024 rows)

  3. · MoU signed, no clearance yet Reported #

    Tata Power signs Memorandum of understanding (MoU) A non-binding agreement between the state and a developer to study and build a project at a site, with a water allocation. More in glossary → for Shirawta (1,800 MW) and Bhivpuri (1,000 MW)

    Details and documents

    ₹13,000 crore for two PSPs in Pune and Raigad.Reported“…MW) in the state. These projects, with an estimated investment of approximately Rs. 13000 Cr, will be situated at Shirawta, Pune (1800 MW) and Bhivpuri, Raigad (1000 MW) districts. The collaboration is poised to drive the state towards its ambitious goal of becomi…”Tata Power releaseReported“…ry’s clean energy landscape</p>\r\n<p>2. 1800 MW Pumped Hydro Storage Project to be located at Shirawata, Pune district and 1000 MW PSP at Bhivpuri, Raigad district</p>\r\n<p>3. Projects will support to Maharashtra Government s goal of achieving a $1 T…”Tata Power release

    Shirawta PSP · Bhivpuri PSP · Tata Power release

Sources

Confidence: verified